Retainage calculator for progress billing

Retainage is the share of each payment a client holds back until the job is done. Enter the contract value, the retainage percent and the work completed to date, and the calculator shows what this pay application bills and how much is still held.

General information, not legal advice. Your contract sets the terms.

Updated 11 November 2026

The short version

Each pay application bills the net earned to date, which is the work completed less the retainage held, minus whatever earlier applications already billed. The held retainage is not lost. It comes back as its own bill when the client releases it, and on a $100,000 contract at 5% that is $5,000.00.

How a pay application works out

  1. Work completed to date = the part of the contract finished so far, in dollars.
  2. Retainage held to date = work completed x retainage percent.
  3. Net earned to date = work completed - retainage held.
  4. This application = net earned to date - net billed on earlier applications.

Working from totals to date, not from each month's work, means a correction in one month fixes itself in the next application.

A $100,000 contract with 5% retainage

The contract is $100,000 and the client holds back 5%. At 40% complete the work to date is $40,000.00. The client holds $2,000.00 and the first application bills $38,000.00. At 70% complete the work to date is $70,000.00, the retainage held is $3,500.00 and the net earned is $66,500.00. Less the $38,000.00 already billed, the second application is $28,500.00. The calculator above is set to this second step.

Three pay applications on the same contract. The third assumes the job is finished and the client has not yet released the retainage.
ApplicationWork completed to dateRetainage held to dateNet earned to dateBilled beforeThis application
1$40,000.00$2,000.00$38,000.00$0.00$38,000.00
2$70,000.00$3,500.00$66,500.00$38,000.00$28,500.00
3 (job complete)$100,000.00$5,000.00$95,000.00$66,500.00$28,500.00

After the third application the client holds $5,000.00, which is 5% of the whole $100,000. That money is billed once, when the client releases it. If the contract releases half at substantial completion, you bill $2,500.00 then and the other $2,500.00 at final completion.

What goes on the invoice

  • The contract value and the work completed to date.
  • The retainage held, as its own line, with the percent.
  • What earlier applications billed.
  • The amount due on this application.

The progress billing guide goes through the stages of a larger job, and the retainage entry gives the short definition. If your trade bills by stage, the contractor invoicing guide shows how the lines look.

What this calculator does not decide

The contract sets the retainage percent, when it is released and what triggers release. State law can limit or shape those terms, and this page lists no state caps or deadlines. If the client wants to hold more than the contract allows, or will not release it after completion, talk to a construction attorney and read your state's statute.

Common questions

What is retainage?

Retainage is a percentage of each progress payment that the client holds back until the work is finished and accepted. It protects the client if the job is left incomplete or needs fixes. Five and ten percent are common figures, but the contract sets the number.

How do I calculate retainage on a pay application?

Take the work completed to date, multiply it by the retainage percent, and subtract the result to get the net earned to date. Then subtract what earlier applications already billed. At 70% complete on a $100,000 contract with 5% retainage, the work is $70,000.00, the retainage is $3,500.00 and the net earned is $66,500.00.

When do I get the retainage back?

When the contract says it is released, usually after substantial or final completion and any punch list. You bill it as its own amount or on the final invoice. The calculator shows the full amount that will be held at the end, which is the retainage percent times the whole contract.

Is there a legal limit on retainage?

The contract sets the percentage and the release terms, and state law can limit or shape both. This page does not list state rules. Check the statute for your state or ask a construction attorney before you rely on a number.

Is retainage the same as a deposit?

No. A deposit is money paid before the work starts. Retainage is money withheld from payments for work already done. A job can have both.

Should retainage show on the invoice?

Yes. Show the work completed to date, the retainage held as its own line, and the amount billed this time, so the client's accounts team can match each application to the one before.

What this is. A calculator and guide written by InvoiceTools. It is general information, not legal advice. The example job is made up.

Last reviewed by InvoiceTools, Houston, Texas, on 11 November 2026.

Put the application on an invoice

Copy the work completed, the retainage held and the amount due into an invoice and send it as a PDF or a payment link. The generator is free, with no account or card.

The first four documents you send as a tracked link are free with an account. Everything else on InvoiceTools.com stays free. Generators, calculators and downloads need no account; template designs need a free one.